#HeadsUp from the City of Casper

(Casper, Wyo.) - On April 4, 2016, workers will begin a waterline replacement project on Valley Road between 38th Street and Valcarro Road. Also part of the project are South David Street from 50th to 53rd Street and East 8th Street from Long Lane to Carriage Lane. Work will begin on Valley Road and continue to the other sites as work is completed. Each street will be closed to through traffic during the work. Access will be maintained for residents. The project is expected to be complete by August 2016. The cast and ductile iron lines are being replaced with PVC lines. Hydrants in the areas will also be replaced during the project. The replacement is part of general City infrastructure upgrades. The $735,000 project was awarded to Treto Construction, LLC. The project is being funded by Optional One Cent funds, Water Main Replacement funds (generated by water usage bills), and sewer capital funds. For questions or additional information, contact Jason Knopp at (307)